Southeast Power Link public process

On Aug. 1, 2018, SRP filed an application for a Certificate of Environmental Compatibility (CEC) with the Arizona Corporation Commission (ACC) for the Southeast Power Link.

Public process complete

At the conclusion of public hearings, the Arizona Power Plant and Transmission Line Siting Committee unanimously recommended approval of a CEC for the project. On Nov. 7, 2018, the ACC unanimously approved the CEC for the project. The approval is the final step of the application process and enables SRP to move forward with land acquisition, project design and construction. Read press release.

Past events

Date/TimeDetailsLocation
Nov. 7, 2018
10 a.m. 
Arizona Corporation Commission Open MeetingHearing Room One (Opens in a new tab)
1200 W. Washington St.
Phoenix, AZ 85007 
Sept. 6, 2018
1 p.m.
CEC Line Siting Committee Public Hearing

Please note: Hearings are scheduled to continue at 9:30 a.m. on Sept. 7, 10 a.m. on Sept. 10; and will continue beginning at 9:30 a.m. from September 11–14, as necessary.

If a route tour is taken, it will begin at 9 a.m. on Tuesday, Sept. 11. 

Mesa Convention Center (Opens in a new tab)  
Sept. 6, 2018
6 p.m. 
CEC Public Comment Evening Session

Public comment may also be taken at the beginning of each hearing day, or at other times during the hearing at the discretion of the chairman.   

Mesa Convention Center (Opens in a new tab)  
May 14, 2018
5–7 p.m.  
Public open house meeting to gather comments about potential routes. See open house mapChurch of Jesus Christ of Latter-day Saints, Mountain Ranch Ward, 3440 S. Signal Butte Road, Mesa (Opens in a new tab) .