disponible únicamente en inglés

Continued development of Copper Crossing

The continued development will complement the existing solar generation at the site and is expected to feature generating resources needed to support and enable SRP’s transition to a lower carbon resource portfolio.

On this page:
    Page last updated on Wed, Apr. 30, 2025

    About the Copper Crossing Energy and Research Center

    SRP is continuing the development and creation of the Copper Crossing Energy and Research Center on land owned by SRP adjacent to the existing Abel Substation on West Judd Road and the existing Copper Crossing Solar Ranch on West Bella Vista Road in Florence, Arizona.

    The continued development will complement the existing solar generation at the site and is expected to feature generating resources needed to support and enable SRP’s transition to a more sustainable and lower carbon resource mix, including advanced solar technology, two flexible natural gas turbines with a total output of less than 99 megawatts (MW), and small-scale long-duration energy storage (LDES) technologies.

    Presentation on Copper CrossingDocument is a PDF.

    Phase I project information: Flexible natural gas generation

    On Sept. 12, 2022, the SRP Board approved the first phase of continued development at the Copper Crossing Energy and Research Center site (Copper Crossing).

    Phase 1 consisted of the engineering, procurement, construction, commissioning and startup of flexible natural gas generation resources.

    In the summer of 2024, SRP installed two flexible natural gas turbines that generate 99 MW of energy. In addition to the generating facility, there will also be a new 69-kilovolt (kV) substation constructed adjacent to the existing SRP Abel Substation.

    Air permit application

    The 30-day public comment period for the air permit application began on January 26, 2023. A virtual public hearing was held on February 27, 2023. The Pinal County Air Quality District issued an air quality permitDocument is a PDF on May 4, 2023.

    Phase II project information: Advanced solar generation

    On Dec. 5, 2022, the SRP Board approved Phase II Advanced Solar Generation that will be located west of Attaway Road at the Copper Crossing site.

    Phase II details:

    SRP is adding 55 MW of large-scale solar across 270 acres of SRP-owned land. This will generate enough carbon-free energy to power approximately 55,000 average-sized homes a year.

    SRP will develop, own and operate the facility.

    The proposed solar project will provide renewable energy that supports SRP’s 2035 Sustainability Goals.

    Construction activities began in the fall of 2024, and are expected to last through December 2025.

    Phase III project information: Long-duration energy storage pilot projects

    On June 27, 2023 the SRP Board approved Phase III at the Copper Crossing site that will include the installation of long-duration energy storage battery pilot projects. Phase III is an opportunity to study and develop new energy storage technologies to support ongoing research on long-duration energy storage development.

    Phase III details:

    Desert Blume, the first pilot project, will utilize CMBlu Energy’s Organic SolidFlow battery energy storage systemOpen new site.. CMBlu Energy’s first-of-a-kind Organic SolidFlow long-duration energy storage system is made from abundant and easily sourced raw materials, and is easily recyclable, eliminating many concerns often associated with lithium-ion batteries. CMBlu’s technology also uses non-flammable materials and is expected to offer a longer lifespan than conventional lithium-ion batteries, an important factor for long-running utility electric system equipment.

    This pilot project supports ongoing research on long-duration energy storage development.

    SRP selected this innovative technology from a competitive bidding process that sought alternatives to lithium-ion batteries with a 10-hour duration to enable storing daytime solar energy for nighttime use.

    This project is expected to store enough energy to power 1,125 homes for 10 hours.

    Desert Blume project anticipated timeline:

    • 2025 – start construction
    • 2026 – project is completed and operational

    Press Release - Salt River Project and CMBlu Energy Announce Launch of Innovative Long-Duration Energy Storage Project

    On June 26, 2024, SRP issued a Request for Proposal (RFP) for a second long-duration energy storage project at the Copper Crossing site with a target operation date of no later than 2028. SRP is searching for projects with a capacity of 5 MW and a duration of 10 hours.

    In response to the RFP, on November 22, 2024, SRP received 12 proposals for long-duration energy storage technology pilots. SRP is evaluating those proposals and expects to complete the RFP process and announce the selected bidder in the fall of 2025.

    Press Release - SRP Issues RFP for Long Duration Energy Storage Projects

    SRP is working with the Electric Power Research Institute (EPRI) to evaluate the performance of both pilot projects and will use the findings to make decisions that will inform how SRP meets our 2035 Sustainability Goals.

    Contact us

    For questions about the Copper Crossing Energy and Research Center, please call (602) 236-2872 or email 2872line@srpnet.com.