Hayden Generating Station
SRP share: 50% of Unit 2
Location: Four miles east of Hayden, Colo.
Description: Two coal-fired generating units
Capacity: 446 MW from two units. Unit 1 produces 184 MW; Unit 2 produces 262 MW, with SRP receiving 131 MW.
Plant construction: Unit 1 construction began in 1962 and was completed in 1965. Unit 2 construction began in 1973 and was completed in 1976.
Ownership summary:
| Unit 1 |
| PSC |
75.5% |
| PacifiCorp |
24.5% |
| Unit 2 |
| SRP |
50.0% |
| PSC |
37.4% |
| PacifiCorp |
12.6% |